Installation
INSTALLATIONPITCHING STOPPER
1) Install the pitching stopper.
Tightening torque:
T1: 50 N-m (5.1 kgf-m, 36.9 ft-lb)
T2: 58 N-m (5.9 kgf-m, 42.8 ft-lb)
2) Install the air intake chamber and intake boot.
3) Connect the ground cable to battery.
TRANSMISSION REAR CROSSMEMBER & REAR CUSHION RUBBER
1) Install the rear cushion rubber to the transmission.
Tightening torque:
40 N-m (4.1 kgf-m, 29.5 ft-lb)
2) Attach the crossmember to the rear cushion rubber.
Tightening torque:
35 N-m (3.6 kgf-m, 25.8 ft-lb)
3) Install the crossmember.
Tightening torque:
75 N-m (7.6 kgf-m, 55.3 ft-lb)
4) Remove the transmission jack.
5) Install the heat shield cover.
6) Install the front exhaust pipe, rear exhaust pipe and muffler.
7) Connect the ground cable to battery.