Signal Generator Pick-Up Coils
***UPDATED BY TSB# EN91-007, JUNE 19911. Disconnect the wiring connector near the distributor.
Checking Resitance:
2. Connect one end of an ohmmeter to the G1 terminal. Connect the other end to the G- terminal.
G1 Pickup Coil Resistance: 125 - 190 ohms
3. Connect one end of an ohmmeter to the G2 terminal. Connect the other end to the G- terminal.
G2 Pickup Coil Resistance: 125 - 190 ohms
4. Connect one end of an ohmmeter to the NE terminal. Connect the other end to the G- terminal.
NE Pickup Coil Resistance: 155 - 240 ohms
G1 And G2 Pick-up Air Gap:
NE Pick-up Coil Air Gap:
5. Using a non magnetic feeler gauge, measure the gap between the signal rotor and pickup coil projection.
Air Gap: 0.008 in (0.2 mm) or more
NOTE: The air gap is not adjustable. If any of the above tests reveal a pick-up coil outside specifications, replace the distributor housing assembly.