Entire Combination Meter Does Not Operate
METER: METER / GAUGE SYSTEM: Entire Combination Meter does not Operate
Entire Combination Meter does not Operate
WIRING DIAGRAM
INSPECTION PROCEDURE
PROCEDURE
1. INSPECT COMBINATION METER ASSEMBLY
(a) Disconnect the E2 connector.
(b) Measure the resistance according to the value(s) in the table below.
Resistance:
(c) Measure the voltage according to the value(s) in the table below.
Resistance:
NG -- REPAIR OR REPLACE HARNESS OR CONNECTOR
OK -- REPLACE COMBINATION METER ASSEMBLY