Purge Flow Switching Valve
1NZ-FXE EMISSION CONTROL: PURGE FLOW SWITCHING VALVE: INSPECTION
INSPECTION
1. INSPECT PRESSURE SWITCHING VALVE
(a) Inspect the resistance.
(1) Measure the resistance between the terminals.
Standard resistance:
- If the result is not as specified, replace the pressure switching valve.
(b) Check the ventilation.
(1) Check that there is no ventilation from port E to port F.
If there is ventilation, replace the pressure switching valve.
(2) Apply battery voltage across the terminals.
(3) Check that there is ventilation from port F when air is applied to port G.
If there is no ventilation, replace the pressure switching valve.