Diesel Data: Automotive Repair

Installation








2GR-FE ENGINE CONTROL: VACUUM SWITCHING VALVE (for Engine Mounting): INSTALLATION

INSTALLATION

1. INSTALL DUTY VACUUM SWITCHING VALVE





(a) Connect the hose to the duty vacuum switching valve and install the duty vacuum switching valve with the bolt.
Torque: 4.0 Nm (41 kgf-cm, 35 in-lbf)





(b) Connect the 3 vacuum hoses to the duty vacuum switching valve.

HINT:
- Hose A: Large hose
- Hose B: Dummy hose (not used for ventilation, the other end is plugged)





(c) Connect the duty vacuum switching valve connector and clamp.
2. INSTALL NO. 1 AIR CLEANER INLET Installation
3. INSTALL BATTERY Installation
4. INSTALL NO. 2 AIR CLEANER INLET Installation
5. INSTALL V-BANK COVER SUB-ASSEMBLY Installation
6. INSTALL COOL AIR INTAKE DUCT SEAL Installation
7. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
NOTICE: When disconnecting the cable, some systems need to be initialized after the cable is reconnected Repair Instruction - Initialization.

8. INSTALL NO. 2 ENGINE UNDER COVER
9. INSTALL NO. 1 ENGINE UNDER COVER