Installation [12/2019 - 10/2022]: Procedure
- INSTALL OIL COOLER ASSEMBLY
- Install the No. 1 cylinder block insulator and 2 new O-rings.
- Install the oil cooler assembly with the 2 bolts and 2 nuts.
Torque: 21 N.m (214 kgf/cm, 15 ft.lbf)
- Connect the No. 4 water by-pass hose and No. 5 water by-pass hose to the oil cooler assembly, and slide the 2 clips to secure them.
- Install the hose clamp with the nut.
Torque: 10 N.m (102 kgf/cm, 7 ft.lbf)
- INSTALL EXHAUST MANIFOLD ASSEMBLY LH (TWC: Front Catalyst)
Refer to INSTALLATION [12/2019 - 10/2022]
- ADD ENGINE OIL
Refer to PROCEDURE - Step 5 [12/2019 - 09/2020] , or refer to PROCEDURE - Step 5 [09/2020 - 10/2021] , or refer to PROCEDURE - Step 5 [10/2021 - 10/2022]
- ADD ENGINE COOLANT
Refer to PROCEDURE - Step 2
- CHECK ENGINE OIL LEVEL
Refer to PROCEDURE - Step 1
- INSPECT FOR ENGINE OIL LEAK
Refer to PROCEDURE - Step 6 [12/2019 - 09/2020] , or refer to PROCEDURE - Step 6 [09/2020 - 10/2021] , or refer to PROCEDURE - Step 6 [10/2021 - 10/2022]
- INSPECT FOR COOLANT LEAK
Refer to PROCEDURE - Step 3